RIBA Stages:
Services Start Date: February 2022
Services Completion Date: Ongoing 140 Weeks
New build housing on brownfield site, Phase D consisting of three blocks of properties of apartments and houses.
The site is the former paper mill which has had all previous buildings demolished alongside the removal of contaminated waste/land. The site is in a Housing Commitment of over 500 dwellings area as outlined in the Cardiff development plan.
https://www.lovell.co.uk/media/2490/the-mill-brochure.pdf
RIBA STAGE 4 Technical Design
Design Team Meetings, Risk Register
PCI Information Pack, Design proposals and project strategies, checking PC CPP
RIBA STAGE 5 Construction
Attendance at progress meetings
CDM Compliance audits
Agree handover strategy with client
Collate and assess info for H&S file
RIBA Stage 6 Handover and Close out
Finalise and issue H&S file – Digitally
Canton, Cardiff